Exxon to complete Baton Rouge, Louisiana, FCC work by April 5 -sources

By:
Reuters
Updated: Mar 31, 2022, 19:34 GMT+00:00

HOUSTON (Reuters) - Exxon Mobil Corp plans to complete an overhaul of a gasoline-producing fluidic catalytic cracker (FCC) at its 502,500 barrel-per-day (bpd) Baton Rouge, Louisiana, refinery by April 5, said sources familiar with plant operations.

Logo of the Exxon Mobil Corp is seen at the Rio Oil and Gas Expo and Conference in Rio de Janeiro

HOUSTON (Reuters) -Exxon Mobil Corp plans to complete an overhaul of a gasoline-producing fluidic catalytic cracker (FCC) at its 502,500 barrel-per-day (bpd) Baton Rouge, Louisiana, refinery by April 5, sources familiar with plant operations said on Thursday.

Exxon shut the 110,000-bpd PCLA 3 FCC on Feb. 25 for the overhaul, which was scheduled to take seven weeks to complete.

“The Baton Rouge Refinery has shut down some of its units and associated operations for planned maintenance,” said Exxon spokesperson Julie King on Thursday. “We have communicated this turnaround to our customers and expect to meet all contractual commitments.”

The firm also plans to shut in April a 45,000-bpd diesel hydrotreater for planned work that will last until mid-June, the sources said.

PCLA 3 is one of two 110,000-bpd FCCs at the refinery.

(Reporting by Erwin Seba; Editing by Andrea Ricci)

About the Author

Reuterscontributor

Reuters, the news and media division of Thomson Reuters, is the world’s largest international multimedia news provider reaching more than one billion people every day. Reuters provides trusted business, financial, national, and international news to professionals via Thomson Reuters desktops, the world's media organizations, and directly to consumers at Reuters.com and via Reuters TV. Learn more about Thomson Reuters products: